Gannon Dunkerley & Co. Ltd[Construction]{India},National Highways Authority of India (NHAI)[Sponsor]{India},National Highways Authority of India (NHAI)[Sponsor]{India}
项目状态:
Under construction
开始时间:
2016
结束时间:
-
项目说明:
August 2021 - Project is facing slow progress; December 2019 - Construction work 30.72% complete; May 2019 - Gannon Dunkerley Pvt Ltd has failed to meet the last two milestones in the project; February 2016 - Foundation stone has been laid; Project is part of 380 km long Nagaon - Dibrugarh highway project; Project cost - INR2.94bn