India |
项目名称: |
Nagaon - Dibrugarh Four Laning (NH-37), Jorhat - Demow Section Four Laning (NH-37), Assam |
领域: |
Highway/Motorway |
项目类型: |
Upgrade/Maintenance |
项目性质: |
Public |
项目经费 (USD Millions): |
- |
规模: |
82 |
规模单位: |
km |
参加单位: |
Gannon Dunkerley & Co. Ltd[Construction]{India},Voyants Solutions Pvt Ltd[Consultant/Project Management]{India},National Highways & Infrastructure Development (NHIDCL)[Sponsor]{India},Government of India[Sponsor]{India},Isolux Corsan[Construction]{Spain} |
项目状态: |
Under construction |
开始时间: |
2019 |
结束时间: |
2021 |
项目说明: |
August 2021 - Project is facing slow progress; December 2019 - Work progress at Jorhat - Janji section is at 3.8% and Jhanji - Demow section is at 4.26%; September 2019 - NHIDCL recently cancelled the old BOT contracts to Isolux Corsan for project; November 2017 - EPC contract awarded to Gannon Dunkerley & Co; August 2017 - National Highways & Infrastructure Development Corporation invited bids on EPC mode; September 2013 - Project approved; Project will be implemented on Build, Operate and Transfer (BOT-Annuity) in Design, Build, Finance, Operate and Transfer (DBFOT) pattern; Project cost - INR9.63bn (USD125mn) |
发布时间: |
2019 |