National Highways Authority of India (NHAI)[Sponsor]{India}
项目状态:
At planning stage
开始时间:
-
结束时间:
-
项目说明:
June 2021 - Presentation was made here before the Chief Minister regarding proposed alignment of project; August 2020 - Lack of coordination and labour shortage amid pandemic are roadblocks in journey to completion; May 2020 - Tender launched for consultancy services for preparation of DPR; January 2020 - NHAI to invite fresh bids under EPC mode; Construction contract awarded in August 2016 was cancelled in December 2019; Project is part of 89 km Parwanoo (Himachal Pradesh) - Dhalli (Shimla) Four-Laning Project; Project cost - INR12bn