National Highways Authority of India (NHAI)[Sponsor]{India},Airef Engineers[Construction]{India},G R Infraprojects Ltd[Construction]{India}
项目状态:
Under construction
开始时间:
2015
结束时间:
2021
项目说明:
July 2021 - Construction underway; August 2020 - Lack of coordination and labour shortage amid pandemic are roadblocks in journey to completion; May 2020 - Tender launched for consultancy services for preparation of DPR of Kaithalighat-Dhalli section; April 2020 - Work on Parwanoo-Solan and Solan-Kaithlighat sections began which was held up due to lockdown; January 2020 - NHAI to invite fresh bids for Kaithalighat-Dhalli section under EPC mode; August 2015 - Construction contract for Parwanoo-Solan section awarded to G R Infra; Construction contract for Kaithalighat-Dhalli section awarded in August 2016 was cancelled in December 2019; Project comprises of 3 sections, Parwanoo-Solan (39 km), Solan-Kaithalighat (23 km) and Kaithalighat-Dhalli (27 km); Project cost - INR25.18bn