National Highways Authority of India (NHAI)[Sponsor]{India},National Highways Authority of India (NHAI)[Sponsor]{India}
项目状态:
At planning stage
开始时间:
-
结束时间:
-
项目说明:
June 2021 - CM reviews proposed alignment on the project; January 2020 - NHAI to invite fresh bids after the Concessionaire terminated the contract in December 2019; August 2016 - NHAI issued LOA to Chetak Enterprises; May 2016 - Cabinet Committee on Economic Affairs has approved the project; Project will be executed under NHDP Phase III and will have 3 tunnels of a total length of about 2 km, 9 major bridges out of which one would be a cable stayed bridge, 4 minor bridges and 89 culverts; Project cost - INR14.8bn